The Central Electricity Authority (CEA) has notified the National Electricity Plan (NEP) (Vol-I Generation) for the period of 2022-32.
Key points
- The plan document includes the review of the last five years (2017-22), a detailed plan for the next five years (2022-27) and the prospective plan for the next five years (2027-32).
- As per section 3(4) of the Electricity Act, 2003, Central Electricity Authority has been mandated to prepare a National Electricity Plan (NEP) in accordance with the National Electricity Policy and notify such plan once in five years.
- According to the NEP document, the projected All India peak electricity demand and electrical energy requirement is 277.2 GW and 1907.8 BU for the year 2026-27 and 366.4 GW and 2473.8 BU for the year 2031-32 as per 20th Electric Power Survey (EPS) Demand projections.
- The likely Installed Capacity for the year 2031-32 is estimated to be 900,422 MW.
- NEP envisages that the share of non-fossil based capacity is likely to increase to 57.4% by the end of 2026-27 and may likely to further increase to 68.4% by the end of 2031-32 from around 42.5% as on April’2023.